Chimur :- While the construction of Anganwadi was going on at Mouja Ambeneri in Chimur taluk, a slab suddenly collapsed, this has raised doubt on the Anganwadi construction.
It has come forward that the contractor of Anganwadi construction is Harshal Dookre. Due to the collapse of the slab, there is no way to know the quality of iron, mortar, cement, sand, bricks and other materials used in the construction of Anganwadi.
Although the construction of Anganwad is of inferior quality, why is it not paid attention to? This question arises.
There is a cry of the villagers that after 15 to 20 days of construction, the contractor is showing the completion of the construction in two to three days without water.
In Chimur taluka, even though other such constructions have been largely bogus, those constructions are being neglected. Due to this, there is a discussion among the citizens that those who do bogus constructions have silver.
People are of the opinion that the entire construction done in Chimur taluk should be checked by the senior officials at the district level.
Is the huge amount of funds sanctioned for each work for improper constructions? This issue is also critical.
However, there is no way to know what is a celebration and what is a feast due to neglect of improper construction.
It is a fact that their construction bills are being paid blindfolded due to the contractor’s relationship with the ruling party.
As no construction is being carried out as per the estimate, the public is demanding that the guilty contractors and engineers should be investigated and action taken against the guilty contractors and engineers.
Sarpanch, office bearers and contractors of the ruling party are working in Chimur Assembly Constituency. As the ruling party sarpanch, officials and contractors are using the licenses of the license holder contractors, all types of constructions are becoming of inferior quality.
There is also a discussion that fifty percent of the money in this government work is being embezzled. There is a discussion everywhere that such contractors should be investigated by the senior officials and the licenses of the concerned should be canceled and their names should be blacklisted.
Vidarbha Pradesh Executive President of N. World Human Rights Organization Pradeep Ramteke will write correspondence to the Chief Secretary of the Prime Minister’s Office and the Chief Secretary of Maharashtra State and will demand an inquiry into all the constructions in Chimur Assembly Constituency.